Preparing the yacht, documentation, personnel and operational controls required for safe and organised arrival into the shipyard.
Before any yacht enters a shipyard, the Project Manager must confirm that the vessel’s arrival, manoeuvring, lifting and initial work activities are properly coordinated.
The objective of this module is to ensure that the yacht can enter the yard safely, that the necessary authorities and documentation are in place, and that no work begins before responsibilities, insurance, access and technical information have been confirmed.
Before the vessel arrives, the Project Manager should verify that the following documentation is available where applicable:
A 58-metre motor yacht is due to enter the shipyard on Monday morning. The captain has confirmed the ETA, but no pilot booking has yet been made and the Project Manager has not confirmed the port authority requirements.
A. Assume the captain will arrange the pilot
B. Contact the Capitainerie, confirm pilotage requirements, book the pilot if required, and confirm entry costs and timing
C. Wait until the yacht reaches the harbour entrance
D. Ask the shipyard security team to decide
Correct answer: B
Why:
The Project Manager must confirm the local port-entry requirements in advance. Pilotage requirements, timing, costs and coordination with the Capitainerie should be resolved before the vessel approaches the yard.
A yacht is scheduled to be lifted out of the water. The yard has a travel lift with sufficient nominal capacity, but no signed docking plan has been provided.
Question:
Should the lift proceed?
A. Yes, because the travel lift capacity is sufficient
B. Yes, if the captain verbally approves it
C. No. The docking plan and vessel support arrangement must be confirmed before lifting
D. Only if the owner is present
Correct answer: C
Why:
The lift capacity is only one part of the operation. The docking plan is required to establish the correct support positions and avoid structural damage.
The yacht has arrived, but the Project Manager cannot confirm who has authority to approve additional work or whether the yacht’s liability insurance is valid for the yard period.
Question:
What is the correct action?
A. Begin work and resolve the paperwork later
B. Ask subcontractors to start only minor tasks
C. Confirm authority, POA where applicable, insurance and approval responsibilities before work begins
D. Leave the decision entirely to the captain
Correct answer: C
Why:
The Project Manager must establish who has authority to approve work and ensure that insurance and responsibility are properly defined before the yard begins operations.
The yacht has entered the shipyard and the original work list is known, but several crew members have raised additional technical concerns.
Question:
What should the Project Manager organise?
A. Wait until the first weekly progress meeting
B. Hold a welcome / kick-off meeting with the captain and selected crew to confirm scope, questions, access, responsibilities and possible unforeseen work
C. Ask each crew member to contact subcontractors directly
D. Ignore additional concerns until they appear on the work list
Correct answer: B
Before completing this module, the Project Manager should be able to: