Tel: +33768734502| Email : sales@davidjbanks.co.uk

PAINT, COATINGS & ANTIFOULING
Project Manager control of surface preparation, coating application and finish quality
Coating work on a yacht is highly sensitive to surface preparation, environmental conditions, contamination, product compatibility, application method and curing time.
The Project Manager’s role is to coordinate the coating specification, preparation standard, inspection points, subcontractor activities, programme and documentation so that the finished coating system meets the required technical and cosmetic standard.
The objective of this module is to help the Project Manager understand the principal controls required from initial inspection through preparation, application, inspection and final acceptance.
Key responsibilities
COATING CONTROL CHECK
Before and during coating work, the Project Manager should verify, where applicable:
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — Dew Point
Painting is scheduled to begin early in the morning. The air temperature appears acceptable, but the substrate temperature is only slightly above the calculated dew point.
Question:
What should the Project Manager do?
A. Start painting because the air temperature is acceptable
B. Confirm that the substrate temperature meets the coating manufacturer’s required margin above dew point before application
C. Add more thinner to the paint
D. Increase the number of coats
Correct answer: B
Why:
Condensation risk depends on the substrate temperature relative to dew point. Application should only proceed when the environmental conditions meet the coating specification.
Scenario 2 — Surface Contamination
After blasting, a steel surface appears visually clean, but salt testing indicates contamination above the specified acceptance limit.
Question:
What is the correct action?
A. Apply primer immediately before flash rusting occurs
B. Clean the surface and retest until contamination is within the specified limit
C. Apply a thicker primer coat
D. Ignore the result because the surface looks clean
Correct answer: B
Why:
Soluble salts can lead to premature coating failure. Visual cleanliness alone does not confirm an acceptable substrate.
Scenario 3 — Dry-Film Thickness
Inspection shows that the dry-film thickness in several areas is below the coating specification.
Question:
What should the Project Manager do?
A. Accept it if the colour looks correct
B. Review the readings, determine the required corrective coating and remeasure after repair
C. Add antifouling immediately
D. Polish the coating
Correct answer: B
Why:
Required coating thickness is part of the protective system. Areas outside specification should be corrected and verified.
Scenario 4 — Recoat Window
A coating layer was applied several days earlier, and the next coat is now planned. The maximum overcoating interval may have been exceeded.
Question:
What should happen?
A. Apply the next coat without delay
B. Check the manufacturer’s technical data and carry out the required surface preparation before recoating
C. Dilute the next coat
D. Increase the spray pressure
Correct answer: B
Why:
When the maximum recoat interval is exceeded, additional preparation may be required to obtain adequate intercoat adhesion.
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: