DOCKING, LIFTING & DRY-DOCK PLANNING
Project Manager control of lifting, docking and vessel-support operations
Moving a yacht from the water onto a travel lift, syncrolift, dry dock or other support system is a critical operation requiring technical preparation, clear responsibilities and controlled communication.
The Project Manager should confirm that the lifting method, vessel displacement, docking arrangement, structural support positions and yard equipment are appropriate before the operation begins.
The objective is to protect the yacht, personnel and yard equipment while ensuring that the vessel is positioned correctly for the planned refit work.
Key responsibilities
PRE-LIFT & DOCKING CHECK
Before lifting or docking, the Project Manager should verify, where applicable:
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — Travel-Lift Capacity
A 62-metre yacht is booked for haul-out. The travel lift has sufficient nominal capacity, but the yacht has recently taken on fuel and significant stores and the current displacement has not been confirmed.
Question:
What should the Project Manager do?
A. Proceed because the lift is rated above the yacht’s design displacement
B. Confirm the expected lifting weight and operating condition before authorising the lift
C. Ask the captain to estimate the additional weight verbally
D. Lift the yacht slowly and monitor the travel lift
Correct answer: B
Why:
The Project Manager should work with a verified or reasonably substantiated vessel condition. Tank loads, stores and other weight changes can materially affect the lifting operation.
Scenario 2 — Sling Position
The docking plan shows the correct support arrangement, but one proposed travel-lift sling position is close to a stabiliser fin.
Question:
What is the correct response?
A. Continue if the sling does not visibly touch the fin
B. Reposition the sling in accordance with the approved lifting / docking arrangement before lifting
C. Remove the stabiliser fin immediately
D. Ask the crane operator to decide
Correct answer: B
Why:
Sling positioning must account for underwater appendages and permitted structural loading areas. The lift should not proceed until the arrangement is confirmed.
Scenario 3 — Tank Condition
Immediately before haul-out, the captain informs the Project Manager that several tanks are significantly different from the condition assumed during docking preparation.
Question:
What should happen?
A. Continue because liquid loads do not affect docking
B. Reconfirm vessel weight, trim and docking assumptions before proceeding
C. Empty every tank completely
D. Add more keel blocks after the yacht is ashore
Correct answer: B
Why:
Tank condition can affect total weight, trim, list and load distribution. Material changes should be reviewed before the vessel is lifted or supported ashore.
Scenario 4 — Communication During Lift
During the lift, a crew member sees something that may interfere with a sling and begins giving instructions directly to the travel-lift operator.
Question:
What should the Project Manager do?
A. Allow all crew members to communicate directly with the operator
B. Maintain the agreed communication chain and stop the operation if a safety concern requires investigation
C. Ignore the crew member
D. Continue until the yacht is completely clear of the water
Correct answer: B
Why:
Lifting operations require controlled communication. A genuine concern should be acted upon, but conflicting instructions from multiple people create additional risk.
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: