SUBCONTRACTOR MANAGEMENT
Project Manager control of subcontractor selection, scope, coordination, performance and close-out
Yacht refit projects rely heavily on specialist subcontractors. These may include engineering companies, electricians, painters, welders, joiners, HVAC specialists, electronics technicians, riggers, survey companies, interior contractors and OEM service representatives.
The Project Manager’s role is to ensure that each subcontractor has a clearly defined scope, understands the programme and yacht requirements, has suitable access and information, and completes the work to the agreed technical, commercial and quality standard.
Poor subcontractor control can lead to duplicated work, gaps in scope, programme delay, uncontrolled variation, damage to completed work and disputes over cost or responsibility.
Key responsibilities
SUBCONTRACTOR CONTROL CHECK
Before appointment and during subcontracted work, the Project Manager should verify, where applicable:
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — Incomplete Quotation
Three subcontractors quote for the same machinery package. One quotation is significantly cheaper, but it excludes removal, lifting, travel and commissioning.
Question:
What should the Project Manager do?
A. Select the cheapest quotation immediately
B. Normalise the quotations and compare the complete scope, exclusions and total expected cost
C. Divide the three prices by three
D. Ask the Captain to select the contractor
Correct answer: B
Why:
Quotation comparison must be based on equivalent scope. A low headline price may result in a higher final cost if important activities are excluded.
Scenario 2 — Additional Work
A subcontractor discovers additional work and starts immediately, saying that it is necessary to avoid delaying the project.
Question:
What should the Project Manager do?
A. Allow the work and discuss the cost afterwards
B. Record the additional scope, establish technical necessity, obtain a quotation and authorised approval before proceeding wherever practicable
C. Refuse all additional work
D. Ask the subcontractor to hide the cost in the original invoice
Correct answer: B
Why:
Uncontrolled additional work is a major source of budget disputes. Variations should be defined, priced and authorised through the project’s change-control process.
Scenario 3 — Interface Conflict
An electrical subcontractor needs access to an area where the joinery contractor has already started closing panels.
Question:
What should the Project Manager do?
A. Allow the joinery contractor to continue because they arrived first
B. Coordinate the interface and sequence the work so required electrical inspection and completion occur before access is closed
C. Ask both subcontractors to resolve it between themselves
D. Remove the electrical work from scope
Correct answer: B
Why:
The Project Manager must control interfaces between work packages. Poor sequencing can cause rework, damage and programme delay.
Scenario 4 — Invoice Approval
A subcontractor submits a final invoice, but commissioning records, test certificates and several punch-list items remain outstanding.
Question:
What should the Project Manager do?
A. Approve the invoice because physical work appears complete
B. Verify contractual completion requirements and resolve outstanding deliverables before final commercial close-out
C. Reject the subcontractor permanently
D. Ask the accounts department to decide whether the work is complete
Correct answer: B
Why:
Physical completion alone may not constitute contractual completion. Documentation, testing, defects and agreed deliverables form part of the work package and should be considered during invoice approval and close-out.
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: