BUDGET, QUOTATIONS & COST CONTROL
Project Manager control of budget baseline, commitments, variations, expenditure and forecast final cost
Financial control on a yacht refit is not limited to checking invoices. The Project Manager must understand what has been budgeted, what has been quoted, what has been committed, what has actually been spent, what work remains, and what the project is expected to cost at completion.
A useful cost-control system distinguishes between the approved budget, purchase commitments, actual expenditure, pending variations, forecast remaining cost and contingency. These figures should be updated throughout the project so that the owner, Captain or management company receives an accurate financial position rather than discovering overruns at the end.
The Project Manager’s role is to maintain commercial visibility, challenge incomplete or unclear quotations, control additional work, reconcile invoices against approved scope and maintain a realistic forecast of the final project cost.
Key responsibilities
A simple project-control relationship to remember is:
Forecast Final Cost = Actual Cost + Committed / Outstanding Cost + Estimated Cost to Complete
The precise accounting method can vary between organisations, but the Project Manager must avoid double-counting committed, invoiced and forecast costs.
BUDGET & COST-CONTROL CHECK
For each project and work package, the Project Manager should verify, where applicable:
For reporting purposes, the PM should be able to explain the difference between:
Budget — the authorised financial allowance.
Commitment — money contractually or commercially committed to suppliers or subcontractors.
Actual Cost — expenditure already incurred or invoiced, according to the project accounting method.
Accrual — cost for work already performed but not yet formally invoiced or posted.
Estimate to Complete (ETC) — expected cost of remaining work.
Forecast Final Cost / Estimate at Completion (EAC) — the predicted total project cost when all work is complete.
Variance — the difference between the approved budget and forecast final cost.
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — Cheap Quotation
A subcontractor submits a quotation of €38,000. A second contractor quotes €46,000. The cheaper quotation excludes scaffolding, crane hire, travel and commissioning, while the more expensive quotation includes them.
Question:
What should the Project Manager do?
A. Select the €38,000 quotation because it is cheaper
B. Normalise both quotations to the same scope before making a commercial comparison
C. Average the two quotations
D. Select the contractor with the lowest labour rate
Correct answer: B
Why:
Commercial comparison must be made on a like-for-like basis. Excluded items can make the apparently cheaper quotation more expensive once the complete scope is considered.
Scenario 2 — Unapproved Variation
A subcontractor submits an invoice containing €12,500 of additional work that was not included in the original purchase order and was never formally approved.
Question:
What should the Project Manager do?
A. Approve it because the work has already been completed
B. Verify the technical necessity, evidence, authority and commercial basis before accepting the additional cost
C. Reject every variation automatically
D. Add the cost to contingency without recording it
Correct answer: B
Why:
Completed work does not automatically establish commercial entitlement. Variations should be traceable to scope, instruction, approval and supporting evidence.
Scenario 3 — Budget Reporting
The project budget is €1,000,000. Actual invoices total €520,000. A further €310,000 is committed under purchase orders, and the Project Manager estimates another €240,000 will be required to complete the project.
Question:
What is the approximate forecast final cost?
A. €520,000
B. €830,000
C. €1,070,000
D. €1,240,000
Correct answer: C
Why:
Using the simplified project-control approach:
€520,000 actual + €310,000 outstanding commitment + €240,000 estimated remaining cost = €1,070,000 forecast final cost.
Against the €1,000,000 budget, this indicates a forecast overrun of approximately €70,000, assuming there is no double-counting within the figures.
Scenario 4 — Invoice Verification
A contractor invoices 100% of a work package. Physical work appears nearly complete, but commissioning, documentation and several punch-list items remain outstanding.
Question:
What should the Project Manager do?
A. Approve 100% because most physical work is finished
B. Review the contractual completion basis and certify only the amount properly due against verified progress and deliverables
C. Refuse to pay anything
D. Ask the accounting department to estimate the percentage
Correct answer: B
Why:
Invoice approval should be supported by verified scope completion, agreed commercial terms and required deliverables. Physical installation alone may not equal contractual completion.
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: