MACHINERY, ENGINES & GENERATORS
Project Manager control of machinery overhaul, maintenance, testing and commissioning
Machinery work on a yacht may include main engines, generators, gearboxes, pumps, cooling systems, exhaust systems, mounts, fuel systems, lubrication systems and associated controls.
The Project Manager is not expected to replace the Chief Engineer or specialist technician. The PM’s role is to coordinate scope, subcontractors, access, programme, parts, documentation, testing, quality control and final acceptance.
The objective of this module is to ensure machinery work is properly planned, traceable and tested before the yacht returns to service.
Key responsibilities
MACHINERY CONTROL CHECK
Before and during machinery work, the Project Manager should verify, where applicable:
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — Generator Overhaul
A generator overhaul is nearly complete, but several replacement parts have arrived without traceable part numbers or supplier documentation.
Question:
What should the Project Manager do?
A. Install them if they appear identical
B. Confirm correct specification and traceability before installation
C. Ask the crew to decide
D. Install them and record them later
Correct answer: B
Why:
Machinery components should match the required specification and be traceable, particularly on critical equipment.
Scenario 2 — Alignment
A main engine has been removed and reinstalled after major work. The subcontractor proposes starting the engine without checking alignment.
Question:
What should happen?
A. Start the engine and check vibration afterwards
B. Confirm alignment requirements and complete the required checks before operation
C. Increase mount tension
D. Ask the Captain to approve the start
Correct answer: B
Why:
Machinery removal can affect alignment. Incorrect alignment can damage couplings, mounts, shafts, gearboxes and bearings.
Scenario 3 — Cooling System
After recommissioning, a generator reaches an unusually high operating temperature under load.
Question:
What should the Project Manager do?
A. Continue the load test to see whether temperature stabilises
B. Stop or reduce the test as appropriate and investigate cooling-system condition before continuing
C. Increase engine speed
D. Ignore it if there is no alarm
Correct answer: B
Why:
Abnormal operating temperature may indicate a cooling-flow, heat-exchanger, thermostat, pump or system problem and should be investigated before continued operation.
Scenario 4 — Commissioning Records
A machinery subcontractor has completed the work and wants to leave the yard, but no commissioning report or test readings have been provided.
Question:
What should the Project Manager do?
A. Accept the work because the machinery runs
B. Obtain the agreed commissioning records, test results and service documentation before closing the work package
C. Ask the crew to prepare the report
D. Close the job and request the report later
Correct answer: B
Why:
Completion should include objective evidence of testing, commissioning and the final service condition
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: