CLASS SURVEYS & SPECIAL SURVEY PLANNING
Project Manager control of classification status, survey scope, preparation and close-out
Classification societies establish and apply technical rules relating to the design, construction, maintenance and survey of vessels. A classed yacht remains subject to periodic surveys and may also require occasional surveys following damage, major repair, alteration or other significant events.
The Project Manager is not the Class surveyor and does not determine class acceptance. The PM’s role is to understand the yacht’s class status, identify relevant survey requirements, prepare the vessel and documentation, coordinate attendance, maintain survey access, track findings and ensure outstanding items are closed before redelivery.
The objective of this module is to help the Project Manager integrate Class requirements into the refit programme rather than treating survey work as a separate activity that is addressed only at the end.
Key responsibilities
RINA states that class is maintained through periodical and occasional surveys, while its rules separate classification and surveys from hull, machinery, fire protection, materials and welding requirements.
CLASS SURVEY PLANNING CHECK
Before and during a Class survey period, the Project Manager should verify, where applicable:
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — Closing Structure
A structural repair has been completed and the yard wants to reinstall insulation and interior lining immediately. The Class surveyor has not yet inspected the final repair.
Question:
What should the Project Manager do?
A. Close the area to protect the programme
B. Keep the repair accessible until the required Class inspection is complete
C. Photograph the repair and close it
D. Ask the interior subcontractor to decide
Correct answer: B
Why:
Survey hold points must occur before required areas become inaccessible. Closing a repair before inspection can create delay, rework and loss of evidence.
Scenario 2 — Planned Modification
During the refit, the owner requests a structural modification that may affect the approved vessel arrangement.
Question:
What should the Project Manager do?
A. Begin work immediately and submit drawings afterwards
B. Determine whether Class approval is required and obtain the necessary technical approval before irreversible work begins
C. Ask the subcontractor to make the decision
D. Treat it as a cosmetic change
Correct answer: B
Why:
Classification societies review design and technical compliance against their applicable rules. Significant changes may require document or drawing approval before construction proceeds.
Scenario 3 — Outstanding Recommendation
A Class survey has identified an item requiring corrective work, but the yacht is approaching its planned departure date.
Question:
What should the Project Manager do?
A. Ignore the item if the yacht is operational
B. Track the item, coordinate corrective action and confirm the surveyor’s required close-out status before redelivery
C. Remove the item from the project list
D. Ask the Captain to sign it off
Correct answer: B
Why:
Class findings remain subject to the classification society’s acceptance process. The PM should manage the work and evidence but cannot substitute their own acceptance for that of Class.
Scenario 4 — Damage During Refit
While in the yard, significant accidental damage occurs to a classed structural area.
Question:
What is the appropriate Project Manager response?
A. Repair it without notifying anyone if the yard is confident in the repair
B. Determine whether Class notification and an occasional survey are required and coordinate the necessary inspection and repair approval
C. Cover the damaged area until the next annual survey
D. Treat it only as an insurance issue
Correct answer: B
Why:
Occasional surveys may be required following incidents or other significant events affecting the vessel’s classed condition.
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: