Tel: +33768734502| Email : sales@davidjbanks.co.uk

HULL, STEEL & ALUMINIUM STRUCTURES
Project Manager control of structural inspection, repair and refit work
Structural work on a yacht must be planned around the vessel’s original construction, material type, Class requirements, survey findings and the intended scope of repair or modification.
The Project Manager is not expected to replace the naval architect, structural engineer or Class surveyor. The PM’s role is to coordinate the inspection, technical decisions, approved repair methods, subcontractors, documentation, programme and quality control.
The objective of this module is to help the Project Manager recognise structural risks, understand the information required before work begins and maintain traceability from initial defect through repair, inspection and final acceptance.
Key responsibilities
STRUCTURAL ASSESSMENT & REPAIR CHECK
Before structural work begins, the Project Manager should verify, where applicable:
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — Plate Wastage
Ultrasonic thickness measurements identify significant wastage in part of a steel shell plate. The subcontractor proposes welding a doubler plate over the affected area.
Question:
What should the Project Manager do?
A. Approve the doubler because it is faster
B. Confirm the repair method with the relevant technical authority and Class where applicable before proceeding
C. Allow the welder to decide
D. Paint the area and monitor it later
Correct answer: B
Why:
The appropriate repair depends on structural condition, location, Class requirements and approved engineering practice. The PM should ensure the repair method is technically accepted before work proceeds.
Scenario 2 — Aluminium Repair
An aluminium hull plate requires replacement. A subcontractor proposes using aluminium plate available in stock but cannot immediately provide its material certification.
Question:
What is the correct action?
A. Use the plate because all marine aluminium is equivalent
B. Confirm the correct alloy, temper and certification before fabrication
C. Use thicker material to compensate
D. Ask the paint supplier
Correct answer: B
Why:
Aluminium alloys and tempers have specific mechanical and welding characteristics. Material traceability should be confirmed before structural fabrication.
Scenario 3 — Hidden Structure
A repair area will be closed permanently after a new plate is installed, but the internal stiffeners and welds have not yet been inspected.
Question:
What should happen?
A. Close the area to maintain programme
B. Stop and arrange the required inspection before the structure becomes inaccessible
C. Photograph only the outside after welding
D. Ask the owner after completion
Correct answer: B
Why:
Inspection hold points must occur before structural areas become inaccessible. Otherwise important evidence and verification may be lost.
Scenario 4 — Welding Distortion
During replacement of a large plate, visible distortion begins developing in the surrounding structure.
Question:
What should the Project Manager do?
A. Continue until the plate is fully welded
B. Pause the work and review the welding sequence, heat input, restraint and technical repair plan
C. Grind the distorted area flat afterwards
D. Apply additional paint
Correct answer: B
Why:
Structural welding can introduce significant heat and distortion. The operation should be reassessed before further damage develops.
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: