Tel: +33768734502 | Email: opusprojectmaneger@gmail.com.

Project Manager control of budgets, quotations, commitments, variations, forecasting, commercial approvals and final cost reporting during yacht refit.
Cost control is one of the core responsibilities of a yacht Project Manager. A refit budget must remain linked to the approved scope, quotations, committed expenditure, variations, invoices and forecast final cost throughout the project.
The Project Manager is not simply recording expenditure after it occurs. The PM should establish a clear commercial baseline, identify developing cost exposure early, control additional work, maintain approval traceability and provide reliable forecasting to the owner, Captain or management company.
The objective of this module is to help the Project Manager establish disciplined budget control from initial quotation review through commitment, variation management, invoice verification and final financial close-out.
• Establish an approved project budget and cost-control structure.
• Break the budget into logical work packages or cost codes.
• Review quotations for scope, assumptions, exclusions and commercial conditions.
• Compare quotations on a like-for-like basis wherever possible.
• Identify provisional sums, allowances and uncertain cost exposure.
• Record approved commitments when orders are placed.
• Track actual expenditure against the approved budget.
• Maintain visibility of committed cost, invoiced cost and forecast final cost.
• Control variations and additional work through the agreed approval process.
• Prevent unauthorised scope growth and unrecorded commercial commitments.
• Assess the cost impact of technical decisions and programme changes.
• Review subcontractor claims and invoice support.
• Confirm invoices correspond with approved scope, progress and agreed rates.
• Identify budget variance early and communicate the reason.
• Maintain contingency visibility and avoid disguising overruns within unrelated budget lines.
• Forecast the likely final project cost throughout the refit.
• Record commercial decisions, approvals and rejected variations.
• Reconcile final accounts and outstanding commitments before project close-out.
• Provide a clear final financial position for handover and reporting.
The Project Manager should maintain visibility of the following commercial information where applicable:
• approved budget
• work-package budgets
• cost codes
• quotation reference
• quotation revision
• scope included
• exclusions and assumptions
• provisional sums
• agreed rates
• purchase orders or authorised commitments
• committed cost
• invoices received
• invoices approved
• payments where visibility is required
• approved variations
• pending variations
• rejected variations
• forecast additional cost
• contingency remaining
• forecast cost to complete
• forecast final cost
• budget variance
• commercial risks
• outstanding final accounts
A quotation should be reviewed for more than the total price. The Project Manager should verify what is included, what is excluded, what assumptions have been made, whether testing and documentation are included, and what could legitimately create additional cost later.
Where quotations cannot be compared directly, the PM should normalise the scope as far as practicable before making a commercial recommendation.
A variation should identify the change from the original scope, the reason for the change, technical impact, commercial value, programme effect and approving authority.
Where urgent work must proceed before a final price is available, the PM should still establish a written instruction, agreed commercial basis or estimate, approval route and traceable record of the decision.
Two subcontractors have submitted quotations for the same machinery package. One is significantly cheaper, but its quotation excludes commissioning, travel costs and final documentation. The higher quotation includes all three.
What should the Project Manager do before making a recommendation?
A. Select the lowest total price immediately
B. Compare the quotations on a like-for-like basis, including exclusions, assumptions and likely additional costs
C. Select the most expensive quotation because it is probably better
D. Ask the owner to choose without further analysis
The quoted total alone may not represent the real project cost. The PM should normalise the scope as far as practical and identify exclusions, assumptions, provisional items and likely additional charges before making a commercial recommendation.
A subcontractor identifies additional work worth approximately €12,000 and begins immediately because the technician believes it is necessary. No written variation or commercial approval has been issued.
What should the Project Manager do?
A. Allow the work to continue because it appears technically necessary
B. Stop or control the additional scope until the technical need, cost and approving authority are documented, except where immediate action is required for safety or damage prevention
C. Wait for the final invoice before discussing the variation
D. Move the cost into another budget line
Additional work creates both technical and commercial exposure. The PM should establish what has changed, why it is required, the likely cost and programme effect, and who has authority to approve the commitment before uncontrolled expenditure develops.
The approved project budget is €850,000. Current invoices remain within budget, but several known variations and pending work packages indicate that the likely final cost will exceed €900,000.
When should the Project Manager report the developing overrun?
A. Only after the invoices have actually exceeded €850,000
B. At final project close-out
C. As soon as the forecast information provides a reasonable basis to identify the likely variance
D. Only if the owner specifically asks
Effective cost control is forward-looking. The PM should report forecast exposure when it becomes reasonably identifiable, rather than waiting until the money has already been spent. Early visibility allows commercial and technical decisions to be made while options still remain.
A subcontractor submits a final invoice for a completed work package. The invoice includes the original contract value plus several additional charges that do not correspond with any recorded approved variations.
What should the Project Manager do?
A. Approve the invoice because the physical work is complete
B. Pay the invoice and investigate the additional charges afterwards
C. Reconcile the invoice against the approved scope, authorised variations, agreed rates and supporting records before approval
D. Reject the entire invoice without review
Invoice approval should be supported by traceable commercial records. The PM should verify the original commitment, authorised changes, agreed rates, progress and supporting documentation before recommending or approving payment.
Before completing this module, the Project Manager should be able to:
• Establish and maintain an approved project budget
• Structure the budget into logical work packages or cost codes
• Review quotations for scope, assumptions, exclusions and commercial conditions
• Compare competing quotations on a like-for-like basis
• Identify provisional sums, allowances and uncertain cost exposure
• Record approved commercial commitments when orders are placed
• Distinguish between budget, committed cost, invoiced cost and forecast final cost
• Control additional work and variations through the agreed approval route
• Prevent unauthorised scope growth and unrecorded commercial commitments
• Assess the financial effect of technical and programme changes
• Verify subcontractor invoices against approved scope, progress and agreed terms
• Identify budget variance early and communicate the reason
• Maintain visibility of contingency and remaining cost exposure
• Forecast cost to complete and likely final project cost
• Record commercial decisions, approvals and rejected variations
• Reconcile outstanding commitments and final accounts at project close-out
• Provide a clear final financial position for owner or management reporting