GANTT PLANNING & PROJECT CONTROLS
Project Manager control of programme structure, dependencies, milestones, progress and recovery
A yacht refit programme is more than a list of dates. The Project Manager must understand the sequence of work, dependencies between activities, access restrictions, long-lead materials, survey hold points, subcontractor interfaces and the dates that ultimately control redelivery.
A Gantt programme provides a visual representation of activities against time. It allows the Project Manager to identify when work should start and finish, which activities depend on others, where resources or access may conflict and which activities have little or no scheduling flexibility.
The Project Manager’s role is to establish a realistic baseline programme, keep it updated with actual progress, identify delay early and coordinate corrective action before individual delays combine into a redelivery problem.
Key responsibilities
PROGRAMME & PROJECT-CONTROL CHECK
For the master programme and each major work package, the Project Manager should verify, where applicable:
Useful planning terms:
Baseline Programme — the approved reference programme against which subsequent progress and delay are measured.
Dependency — the logical relationship between activities.
Milestone — a significant event or control point, normally with zero duration.
Critical Path — the sequence of activities that controls the earliest calculated completion date of the project.
Float — the scheduling flexibility available before an activity affects a controlling date.
Look-Ahead Programme — a short-term planning view, commonly covering the next one to several weeks, used for operational coordination.
Recovery Programme — a revised execution strategy intended to recover lost time through resequencing, additional resources or other controlled measures.
PROJECT MANAGER COMPETENCY TEST
Scenario 1 — False Progress
A subcontractor reports that a work package is 90% complete. Inspection shows that the physical installation is largely complete, but testing, documentation and commissioning remain outstanding.
Question:
What should the Project Manager do?
A. Record 90% because the subcontractor reported it
B. Assess progress against the defined completion criteria and remaining work before updating the programme
C. Record 100% because installation is complete
D. Remove testing from the programme
Correct answer: B
Why:
Progress should be measured against the full activity or work-package scope. Physical installation alone may not represent near-completion if testing, commissioning and documentation remain outstanding.
Scenario 2 — Dependency
Interior panels cannot be permanently closed until electrical inspection and testing behind them are complete.
Question:
How should the programme reflect this?
A. Schedule both activities independently
B. Establish an appropriate dependency so closure cannot complete before the required electrical work and inspection
C. Allow the joinery contractor to decide
D. Add more float to the interior activity
Correct answer: B
Why:
Dependencies should reflect the real technical sequence of the work. Correct logic helps prevent premature closure, rework and loss of inspection access.
Scenario 3 — Critical Delay
A long-lead component on a critical-path activity will arrive seven days late.
Question:
What should the Project Manager do first?
A. Wait seven days and update the programme afterwards
B. Assess the effect on dependent activities and redelivery, then investigate mitigation or recovery options
C. Remove the activity from the critical path manually
D. Change the baseline date
Correct answer: B
Why:
Critical-path delay can affect the project completion date. The PM should assess the impact immediately and examine alternatives such as resequencing, expedited delivery, temporary arrangements or additional resources where technically and commercially justified.
Scenario 4 — Baseline Manipulation
The project is behind programme. Someone suggests changing the original baseline dates so the current programme no longer shows a delay.
Question:
What should the Project Manager do?
A. Change the baseline to improve the report
B. Preserve the approved baseline and show the current forecast separately
C. Delete all previous programme versions
D. Stop reporting variance
Correct answer: B
Why:
The baseline is the reference against which performance is measured. Current forecasts may change, but altering the historical baseline without formal approved change destroys meaningful variance reporting.
MODULE COMPLETION
Before completing this module, the Project Manager should be able to: